BT Primary School of bulyamushenyi
open
School #47
Sponsored by Building Tomorrow Supporters
Located in the Nakaseke
Community Development Officer: Fred Kijogwa
BT Fellow: None
Groundbreaking
September 5, 2016
Opening
February 6, 2017
Construction Timeline
Main Building
Groundbreaking
September 5, 2016
Foundation Completed
November 1, 2016
Wall Construction Begins
November 20, 2016
Walls Completed
December 5, 2016
Roofing Completed
December 17, 2016
Finishing Touches Completed
February 7, 2017
Latrines & Nursery
Latrines Completed
January 29, 2017
Nursery Completed
February 6, 2017
School Opened
February 6, 2017